路沿石的安装形式
1.路沿石必须挂通线进行施工,按侧平面顶面示高标线绷紧,按线码砌侧平石,侧平石要安正,切忌前仰后合,侧面顶线顺直圆滑平顺,无高低错牙现象,平面无上下错台、内外错牙现象。
1. Lu Yanshi must hang line construction, according to the lateral plane top surface shows high standard line tension, according to the line side flat stone blocks, the flat side of stone to safety is, do bjwudao.89ix.cn bjyuesao.89ix.cn bjdiandongmen.89ix.cn bjzhuangxiu.89ix.cn bjbaojie.89ix.cn bjbanjia.89ix.cn not laugh, the side top line straight smooth, no level of the wrong tooth phenomenon, plane, dislocation, and wrong tooth phenomenon.
2.路沿石必须座浆砌筑,座浆必须密实,严禁塞缝砌筑;
The 2. road along the stone must be masonry, the seat slurry must be dense, and the slit is strictly prohibited.
3.路沿石接缝处错位不超过1mm;侧石和平石必须在中间均匀错缝。
The dislocation of the 3. road along the seam is not more than 1mm; the side stone peace stone must be misaligned in the middle.
4.路沿石侧平石应保证尺寸和光洁度满足设计要求。外观美观,对弯道部分侧石应按设计半径专门加工弯道石,砌筑时保证线形流畅、圆顺、拼缝紧密。弧形侧石必须人工精凿后抛光处理。
4. road along the stone Ceping stone should ensure the size and finish to meet the design requirements. Beautiful appearance, should be designed according to special processing of stone on the curve bend radius part side of the stone masonry, to ensure the smooth, round, linear seam closely. The curved side stone must be polished and treated manually.
5.路沿石后背应还土夯实,夯实宽度不小于50mm,厚度不小于15mm。
The back of the 5. road along the back of the stone should be rammed and rammed, the rammed width is not less than 50mm, and the thickness is not less than 15mm.
6.路沿石勾缝:勾缝时必须再挂线,把侧石缝内的杂物剔除干净,用水润湿,然后用1:2.5水泥砂浆灌缝填实勾干。
6. Lu Yanshi: must hang pointing pointing to the side of the line, crevice debris removed clean, water wetting, and then use the seam filled hook dry filling 1:2.5 cement mortar.
7.侧平石勾缝、安砌后适当浇水养护。
7. side flat stone pointing, laid after appropriate water conservation.